Why software estimates slip, and how to plan for it
TL;DR
Difficulty: Intermediate
Software runs late because early estimates are made before the decisions that would make them accurate, and because everyone, clients included, pictures the plan going right.
- Ask for ranges and a P80 date, not one day.
- Turn each part into optimistic, most likely and pessimistic figures and work out the expected value.
- Check the result against how the supplier's similar past projects really went, and budget for that.
- Build the riskiest part first and ship usable milestones in order of importance.
What to read first
Software is late so often that people treat it as a law of nature. It is not, but it is predictable. Here is why estimates slip, how to turn a supplier's single date into an honest range, and how to plan a project so that a slip costs you contingency you set aside rather than a promise you made.
Late is the normal case, so plan for it
You have a brief, you have chosen how to pay, and now someone gives you a date. Somewhere in the back of your mind a voice says: software is always late. That voice is right more often than it is wrong, and it is not because developers are lazy or dishonest. It is because an estimate made before the details are known is a guess about things nobody has decided yet.
This article explains why estimates slip, in plain words, and then shows you how to plan so that a slip does not hurt. You will see where the uncertainty comes from, why everyone (you included) is too optimistic, two simple ways to correct for it, and how to read a supplier's estimate so you can tell an honest range from a hopeful date.
The example runs through the whole series. Calder Physio is an invented group of three physiotherapy clinics in Manchester (calderphysio.example). Its owner, Rachel, is commissioning her first bespoke software: online booking, a patient portal, payments for self pay patients, reminders by email and text, and an export for the accounts. Her supplier is invented too.
Early estimates are wide because the project is still undecided
In his 1981 book Software Engineering Economics, Barry Boehm showed that the error in an estimate depends on how far the project has got when the estimate is made1. Steve McConnell later drew the same pattern as the cone of uncertainty and put numbers on it2. At the very first idea, an estimate made by a skilled estimator can turn out four times too low or four times too high. Once the vision is agreed, the range shrinks to half or double. Once the requirements are written down, it is roughly two thirds to one and a half times. Once the screens are designed, it is about 0.8 to 1.25 times2.
Read that again, because it changes how you hear a first quote. A figure given on the first call is not wrong. It is simply a point inside a very wide range, and the range is the honest answer.
Example: Rachel's estimate as the cone narrows
Rachel's first call with the supplier lasts 40 minutes. At the end the developer says "this feels like about 400 hours". Using the cone's multipliers, that means anything from 100 hours (400 times 0.25) to 1,600 hours (400 times 4).
Rachel then sends her written brief, the one from writing a software brief a developer can quote on. The supplier now estimates 420 hours, with a range from 210 (420 times 0.5) to 840 hours (420 times 2).
A paid discovery fortnight produces the user stories and acceptance examples. The estimate becomes 440 hours, and the range 295 to 660 hours (440 times 0.67 and 440 times 1.5).
Finally the screens are designed and Rachel clicks through them with two of her therapists. The estimate is 457 hours, with a range from 366 to 571 hours (457 times 0.8 and 457 times 1.25).
The middle figure barely moved, from 400 to 457. The range collapsed from 1,500 hours wide to about 200. That is the real progress of the first two months, and it is worth paying for.
The cone narrows only when you make decisions
There is a catch in the cone that most people miss. It shows the best case. McConnell is explicit: the cone is the accuracy skilled estimators reach on a project that is driving out its uncertainty. It does not narrow because time passes. It narrows because someone decides what the software will do and, just as important, what it will not do. If the scope keeps moving, the cone becomes a cloud that lasts until the end2.
So the person who narrows the cone is often you. Every open question you close is worth more than another week of the developer polishing the estimate.
Example: three decisions that took 150 hours of doubt out
After the discovery fortnight, the supplier lists the three questions creating the most doubt. Rachel answers each one in writing.
- Should patients be able to book a block of six sessions at once? Rachel decides: not in the first version. Patients book one session at a time, and reception can still book a block by hand.
- Do the insurers who pay for some patients need their own login? Rachel decides: no. Insured patients book like everyone else, and the clinic invoices the insurer as it does today.
- Should the reminders go out on WhatsApp as well as email and text? Rachel decides: email and text only, WhatsApp is a later idea.
The supplier removes about 150 hours of "might be needed" from the high end of the range. Nothing was built yet. The saving came entirely from three sentences Rachel wrote.
Everyone plans the best case, including you
The second reason software runs late is human. Daniel Kahneman and Amos Tversky named it the planning fallacy in work first published in the late 1970s: when we predict how long our own task will take, we picture the plan going right and ignore what usually happens to plans like ours3.
Roger Buehler, Dale Griffin and Michael Ross tested it in 1994. They asked psychology students when they would finish their final year thesis. On average the students predicted 33.9 days. They also gave an estimate for "if everything goes as poorly as it possibly could": 48.6 days. The real average was 55.5 days, and only about 30% finished within the time they had predicted4. Even the worst case was too hopeful.
Developers are people, and so are clients. The supplier's estimate leans optimistic, and so do your own promises about the things you will provide.
Example: Rachel's own tasks
The plan relies on Calder Physio delivering four things. Rachel writes down how long she thinks each will take, then checks how long the same kind of job took the last time the clinics did something similar (the move to new accounting software two years ago).
| Task for the clinic | Rachel's first guess | Last comparable job took |
|---|---|---|
| Export a sample of 200 patient records for the migration test | 1 week | 3 weeks (the old system needed its vendor to run the export) |
| Write the reminder and confirmation texts | 2 days | 2 weeks (two rounds of comments from the senior physio) |
| Get two therapists per clinic to test each milestone | 1 week per milestone | 2 weeks per milestone (clinic diaries were full) |
| Sign off the price list and cancellation rules | 1 day | 10 days (needed the accountant) |
Rachel's guesses add up to about three weeks of client side work. Her own history says nearer eight. She puts eight in the plan and tells the supplier, because a project late "because of the client" is still late.
A three point estimate turns one guess into a range
A single number hides the doubt. A three point estimate asks for three numbers for every part of the work: the optimistic case, the most likely case and the pessimistic case. The method comes from PERT, the programme evaluation and review technique, first published in 1959 by the team that developed it5. It combines the three figures into one expected value:
where is the expected effort, is the optimistic estimate (everything goes well), is the most likely estimate, and is the pessimistic estimate (the things that usually go wrong do go wrong). The most likely case counts four times, the two extremes once each, and the six divides by the total weight. An expected value is a weighted average of possible outcomes, explained step by step in Foundations: expected value.
The same method gives a rough measure of how uncertain each part is:
where is the standard deviation of the effort, a measure of spread, is the pessimistic estimate and is the optimistic estimate. A bigger means a part you know less about. The idea of spread is in Foundations: spread.
Why this helps: work rarely finishes much earlier than planned, but it can finish much later. The pessimistic figure pulls the expected value up, and that is exactly the correction a single "most likely" figure leaves out.
Example: Calder Physio's estimate, part by part
At the screens designed stage, the supplier gives Rachel three figures for each part, in hours. The expected value and spread are worked out with the two formulas above.
| Part of the work | |||||
|---|---|---|---|---|---|
| Online booking and clinic diaries | 80 | 110 | 180 | 116.7 | 16.7 |
| Patient portal | 60 | 80 | 130 | 85.0 | 11.7 |
| Payments for self pay patients | 30 | 40 | 70 | 43.3 | 6.7 |
| Reminders by email and text | 20 | 30 | 50 | 31.7 | 5.0 |
| Export for the accounts | 15 | 20 | 40 | 22.5 | 4.2 |
| Link to the practice management system | 40 | 80 | 240 | 100.0 | 33.3 |
| Migrating existing patient records | 30 | 50 | 120 | 58.3 | 15.0 |
| Total | 275 | 410 | 830 | 457.5 | about 43 |
Take the first row step by step. Four times the most likely 110 is 440. Add the optimistic 80 and the pessimistic 180 and you get 700. Divide by six: 116.7 hours. Its spread is 180 minus 80, which is 100, divided by six: 16.7 hours.
The total of the expected values is 457.5 hours, 47.5 hours more than the 410 you would get by adding up the "most likely" figures. That gap is the optimism a single figure hides.
For the total spread you cannot simply add the seven spreads. For parts that do not affect each other, you square each spread, add the squares and take the square root. The squares add up to about 1,837, and the square root of that is about 43 hours.
Now look at one row. The link to the practice management system (the software where the therapists' diaries already live) is about a fifth of the expected hours but contributes 1,111 of those 1,837, about 60% of the total uncertainty. That single number tells Rachel where the risk is, and it shapes everything that follows.
Check the estimate against how similar projects really went
A three point estimate is still built from the inside: the people looking at this project imagining how it will go. Kahneman and Tversky's remedy for the planning fallacy is to start from how things turned out for a whole class of similar cases, and only then adjust for what is special about yours3. Bent Flyvbjerg calls this the outside view and turned it into a method called reference class forecasting: pick a class of comparable past projects, look at how far their real results landed from their estimates, and adjust your estimate by the same pattern6.
Software needs this badly. Flyvbjerg and Alexander Budzier analysed 1,471 IT projects. The average cost overrun was 27%, but one project in six went over its cost by 200% on average and over its schedule by almost 70%7. The average hides a long tail, and a long tail is what sinks a small business.
You will rarely find a public reference class for "booking system for three physiotherapy clinics". But your supplier has one: their own past projects. Ask for it.
Example: Rachel asks for the supplier's track record
Rachel asks: "For your last ten projects of a similar size, how far did the final effort land from the most likely estimate you gave at this stage?" The supplier (invented, like the figures) answers honestly:
Here is how Rachel reads it, step by step.
- Sort the overruns, smallest first, as in the chart: 0, 10, 15, 20, 30, 35, 40, 50, 65 and 110%.
- The middle of the list sits between the fifth and sixth projects, 30% and 35%. So half the projects ran more than about 32.5% over.
- Eight of the ten finished within 50% over. If Rachel wants to be about 80% sure of her budget, she should allow 50% on top of the most likely figure.
- The most likely total from the three point estimate is 410 hours. Adding 50% gives 615 hours.
The inside view said 457.5 hours expected. The outside view says plan nearer 600. When the two disagree, the outside view deserves more weight, because it already contains everything that went wrong on projects that also looked fine at this stage.
Rachel sets her budget at 600 hours. At an invented rate of £90 an hour, the expected cost is £41,175 (457.5 times 90) and the budget she can defend to herself is £54,000 (600 times 90). The difference, £12,825, is her contingency, kept aside and not promised to anyone. How contingency works under each pricing model is in fixed price, time and materials, or a retainer.
Ask for dates with a confidence, not a single day
A date on its own sounds certain and is not. A useful date comes with a confidence: "this date is 50% likely, and that one 80% likely". Project people call these the P50 and the P80. The P50 is a coin toss. The P80 is the date you can tell your staff about.
Example: turning hours into two dates
Rachel and the supplier agree that the developer works about 30 hours a week on Calder Physio. The project starts on Monday 4 January 2027.
- The expected effort, 457.5 hours, divided by 30 hours a week is about 15.2 weeks. That lands around Tuesday 20 April 2027. This is roughly the P50.
- The budget figure from the reference class, 600 hours, divided by 30 is 20 weeks. That lands on Monday 24 May 2027. This is Rachel's P80.
- Her own eight weeks of client side work run alongside the build, not on top of it, but only if the sample records and test days arrive when the plan needs them. She marks those dates in her diary as hard deadlines for herself.
Rachel tells her three clinic managers "live by the end of May". If it arrives in April, that is a pleasant surprise. If she had announced 20 April, there was a one in two chance of disappointing everyone.
Name the unknowns that blow estimates
Most big slips come from a short list of causes that are visible in advance if you look for them.
- Integrations: another system's interface is badly documented, slow or does not do what its sales page says.
- Data migration: old data is messier than anyone thought, with duplicates, missing fields and free text where dates should be.
- Third parties: a payment provider's account checks, a text message sender's registration, a vendor who has to run an export.
- Changing minds: a new idea halfway through, often a good one, that quietly adds weeks.
- Your own side: test days, sign offs and content that arrive later than planned (the planning fallacy, again).
Writing them down is not pessimism. It is how each unknown gets an owner and a date by which it stops being unknown.
Example: Rachel's unknowns list
| Unknown | Why it could blow the estimate | How it gets resolved, and by when |
|---|---|---|
| Practice management system link | Its interface may not allow writing appointments back | Three week test build at the start (week 3) |
| Patient records migration | 6,000 records typed by hand over ten years | Sample of 200 records cleaned and imported (week 4) |
| Text message sender | Sender name registration may take time | Rachel applies in week 1 (week 3) |
| Payment provider account | Checks on a healthcare business may take longer | Rachel opens the account in week 1 (week 4) |
| New ideas from the therapists | Each one adds days | Collected on a "later" list, reviewed only at milestones |
Do the riskiest part first
If one part carries most of the uncertainty, build a small piece of it before anything else. Developers call this a spike or a proof of concept: a short, throwaway piece of work whose only job is to answer a question. Doing the hard part first narrows the cone where it is widest, and if the answer is bad, you find out in week three, not in month four with most of the budget spent.
Example: the practice management system test
The supplier proposes three weeks, fixed at 60 hours, to prove the link to the practice management system before the rest of the build starts. The question is simple: can the new booking system read the therapists' free slots and write a booked appointment back into their diary, reliably?
In the invented outcome, reading slots works on day four. Writing appointments back works too, but only through a slower route, and the developer measures it: 110 hours for the link instead of the expected 100. The pessimistic case of 240 hours is now off the table. The spread for that row drops from 33 hours to under 10, and the spread of the whole project falls from about 43 hours to about 29 after three weeks. That is the best use of 60 hours in the whole budget.
Plan milestones that deliver usable software
A milestone that says "back end 60% complete" tells you nothing you can check. A milestone that says "patients at the Didsbury clinic can book online" is something you can try with your own phone. Usable milestones do three jobs at once: they show real progress, they let your staff find problems early, and if money or time runs out, you stop with something that works rather than half of everything.
Each milestone should pass its own tests and its own sign off before the next one starts. In my own practice I work test first, every release goes through a test gate and into a release register, and verified critical paths are frozen behind an approval step, so a milestone that was accepted stays working. What "accepted" should mean is the subject of acceptance and done. Finding the journeys that must never break is in the critical path in software.
Example: five milestones for Calder Physio
| Milestone | What staff and patients can do afterwards | Planned week (P50) |
|---|---|---|
| 1. Integration test | Nothing visible yet, but the riskiest question is answered | 3 |
| 2. Booking at one clinic | Patients book online at the Didsbury clinic, reception sees bookings in the diary | 7 |
| 3. All clinics and reminders | All three clinics take online bookings, reminders go out by email and text | 10 |
| 4. Payments and migration | Self pay patients pay online, existing patients are in the new system | 13 |
| 5. Portal and accounts export | Patients see their appointments and invoices, the bookkeeper downloads the monthly export | 15 |
Notice the order. The patient portal, which is pleasant but not essential, comes last. If the project hits trouble in week 12, Calder Physio still has online booking, reminders and payments running in all three clinics. More on choosing what ships first is in time to market.
How to read a supplier's estimate
You do not need to know how to build software to judge an estimate. You need to know what an honest one contains. Look for these:
- A breakdown into parts you recognise, not one total.
- Ranges, or optimistic and pessimistic figures, not just one number per part.
- Written assumptions: what the supplier took for granted (for example "the practice management system has a documented interface").
- What is excluded, so you can see what is not in the price.
- The riskiest parts named, with a plan to reduce the risk early.
- Points where the estimate will be checked and updated, such as after discovery or after the integration test.
- What you have to provide, and by when.
And watch for these warning signs:
- An exact date to the day at the first call.
- A total that lands, by coincidence, exactly on your budget.
- "No problem" when you ask for the same scope in half the time.
- No assumptions written down at all, which means every surprise becomes your cost later.
- Fixed scope, fixed date and fixed price all promised before anyone has seen the detail.
Comparing whole proposals, not just the estimate, is the subject of reading a software proposal. Transparent pricing helps here too: I publish my package prices and my hourly rates, so anyone can turn an estimate in hours into money without asking.
Example: two estimates, side by side
Rachel receives two estimates for the same brief (both suppliers invented).
Supplier A writes: "Launch on 1 April 2027. Total £38,000." Nothing else.
Supplier B writes: "Expected effort 440 to 480 hours, budget 600 hours for 80% confidence. Assumes the practice management system allows writing appointments back; we test this first in a three week, 60 hour piece of work. Excludes the WhatsApp reminders and block bookings. You provide 200 sample records by week 4. We estimate again after the integration test."
Supplier A looks less expensive and more confident. Rachel sends A five questions: what does the £38,000 assume about the practice management system? What happens to the price and the date if it does not allow writing back? What is excluded? What do you need from us, and by when? How did your last five similar projects compare with their first estimate?
If A answers well, the two can be compared fairly. If A answers "don't worry, it will be fine", Rachel has learnt what she needed to know.
When it slips anyway, cut scope, not quality
Even a good plan slips sometimes. What you do in the first week of a slip decides whether it stays small. Three moves help: ask for a fresh estimate of the remaining work, with ranges, rather than an apology; look at the milestone list and move the least essential feature to a later phase; and protect testing, because a project that saves time by skipping tests usually loses that time again after launch, with patients watching. If a project is in real trouble, with deadlines missed repeatedly and nobody able to say why, that is a different situation, covered in when a software project goes wrong.
Example: week 9, the migration is harder than planned
In week 9 the supplier reports that the full patient records migration needs 95 hours, not 58. The records contain duplicate patients across the three clinics, which have to be merged carefully. Rachel's options:
- Spend 37 hours of contingency. The expected total rises to 504.5 hours (457.5, plus 10 for the integration, plus 37 for the migration), the expected finish moves about a week later, and 95.5 hours of contingency remain inside the 600 hour budget.
- Move the patient portal (milestone 5) to a second phase and keep the May date.
- Ask for the duplicate merging to be skipped. She rules this out at once: duplicate patients would mean wrong records and wrong reminders, which is exactly the kind of quality cut that costs more later.
She chooses the first option, because the contingency exists for precisely this, and keeps the second as her fallback if another surprise arrives. The budget of 600 hours is unchanged, so the date her staff were told, end of May, still holds.
Conclusion: plan for the range, not the date
Software estimates slip because early estimates are made before the decisions that would make them accurate, and because everyone, clients included, pictures the plan going right. You cannot remove that uncertainty by asking for a firmer number. You can shrink it by making decisions, measure it with a three point estimate, correct it with the outside view of similar past projects, and contain it by doing the riskiest part first and shipping usable milestones in order of importance.
Rachel's plan did all five. She asked for ranges instead of a date, budgeted 600 hours where the most likely figure was 410, tested the risky integration in the first three weeks, and announced the P80 date rather than the P50. When the migration surprised her, the slip cost her contingency she had already set aside, not a promise she had made to her staff.