Fixed price, time and materials, or a retainer: who carries the risk
TL;DR
Difficulty: Intermediate
The pricing model decides who pays when something turns out harder than expected.
- Fixed price: the supplier carries the overrun, but only for what the brief pins down, and charges a margin for it.
- Time and materials: you carry the overrun and get flexibility, so you need weekly visibility and a contingency.
- Capped time and materials: flexibility with a known worst case.
- A paid discovery first, then a fixed price: the best route when one part is unknown.
- Retainers are for after launch, not the first build. Compare quotes by expected cost and worst case, not the headline number, and write the change rate into the contract.
What to read first
Three suppliers, three quotes, three pricing models. The numbers differ, but the bigger difference is hidden: each one hands you a different share of the risk. This chapter shows who pays when the work turns out harder than expected, worked through on an invented physiotherapy clinic in Cork.
Every price is a decision about risk
You have a brief. Three suppliers have read it. One quotes a fixed price, one sends a day rate and an estimate, one offers a monthly retainer. The numbers look different, but the bigger difference is hidden underneath: each one hands a different share of the risk to you.
Risk here means one plain thing. Something will turn out harder than anyone expected, and somebody pays for the extra work. The pricing model decides who.
This chapter answers the question every owner asks at this stage: which pricing model protects me, and what does each one really cost? It builds on writing a brief a developer can quote on, because no pricing model survives a vague brief. If you have not written yours yet, start there.
Through the whole series I use one invented example, and a good few of the lessons hang on it. Lee Valley Physio runs three physiotherapy clinics in and around Cork (leevalleyphysio.example, made up for this series). Its owner, Orla, wants her first bespoke software: online booking with a patient portal, card payments for self pay patients, reminders by email and text, an export for the accountant, and a link to the private health insurers so that a patient's cover can be checked before the first session. That last item will matter a lot.
Example: the same brief, three envelopes
Orla sends her brief to three suppliers (all invented). Here is what comes back.
| Supplier | Pricing model | What the quote says |
|---|---|---|
| Shandon Digital | Fixed price | €60,000 for everything in the brief, paid in three stages |
| Mardyke Software | Time and materials | €600 a day, estimated 80 days, so about €48,000 |
| Douglas Code | Capped time and materials | €620 a day, estimated 80 days, never more than €58,000 |
The lowest number is Mardyke's €48,000. The question this chapter answers is whether it is the lowest cost. It may not be, and the reason is the insurer link.
Fixed price: the supplier carries the risk, and charges for carrying it
A fixed price means the supplier promises to deliver what the brief describes for one agreed sum. If the work takes longer than they thought, they pay for the extra days, not you.
That sounds like the safe choice, and for a well understood job it often is. But nobody carries risk for free. A sensible supplier adds a margin to cover what might go wrong. The UK government's own guidance for buying digital work put it plainly: a fixed price "can be more expensive because the supplier owns most of the risk"1. You pay that margin whether the risk happens or not.
There are two more things to know.
The scope has to be precise. A fixed price covers exactly what is written down, no more. If a requirement is vague, the supplier will build the smallest version that honestly meets the words. If you want more, that is a change.
Changes become the expensive part. Once the contract is signed, you can no longer shop around. Every change goes back to the same supplier at whatever price they set. A supplier who quoted low to win the work can recover the margin through change requests. Not every supplier does this, but the contract makes it possible, so the change rate belongs in the contract before you sign (more on that further down).
Example: Shandon's €60,000 and the insurer link
Shandon's fixed price includes the line "integration with private health insurers for eligibility checks". Orla assumed the insurers offer a simple online connection. Halfway through the build, Shandon finds that the biggest insurer only accepts a file uploaded once a day, with a manual approval step.
Two outcomes are possible, and the contract decides which.
- The brief described the result ("a receptionist can see whether a patient's cover is confirmed before the first session"). Then the harder route is Shandon's problem. They spend 25 extra days and Orla still pays €60,000.
- The brief described a method ("connect to the insurers' live API"). Then Shandon can argue that the file upload is new work, and send a change request: 25 days at their change rate of €750 a day, so €18,750 more. Orla now pays €78,750.
Same project, same problem, an €18,750 difference that came down to one sentence in the brief. A fixed price only moves risk to the supplier for what the brief actually pins down.
Time and materials: you carry the risk, and you get the flexibility
Time and materials means you pay for the time actually spent, at an agreed day or hourly rate, plus any agreed costs (licences, hosting, outside services). The estimate is a forecast, not a promise.
The same government guidance is just as plain about this side: time and materials "means you own more of the risk"1. If the work takes longer, you pay for longer.
In return you get two real benefits. First, there is no risk margin in the price, so if things go to plan you pay less than a fixed price. Second, you can change your mind without a negotiation. You learn something from the first patients using the booking screen, you change direction next week, and you simply pay for the days that takes.
That flexibility only works if you can see what is happening. With time and materials you need, at the very least:
- a weekly report of days used, what they were used for, and the days left against the estimate
- working software you can try at the end of every week or two, not a promise that it is "nearly done"
- an early warning the moment the estimate is likely to be wrong, not at the invoice
Without that visibility you are signing a blank cheque.
Example: Mardyke's €48,000 that becomes €63,000
Mardyke estimates 80 days at €600, so €48,000. When the insurer link turns out to need the file upload, Mardyke spends 25 extra days. Orla pays for them.
where is the total cost in euro, the number of days actually worked and the day rate in euro.
So the lowest quote becomes €63,000, more than Shandon's fixed price in the good case. If the insurer link had been simple, Orla would have paid €48,000 and saved €12,000 against Shandon. Time and materials is a bet that things go roughly to plan, and you hold the bet.
Capped time and materials: flexibility with a ceiling
Capped time and materials is the middle road. You pay for time spent at a day rate, as with time and materials, but the contract sets a ceiling. In the government's description, if the limit is reached before the work is finished, the supplier has to complete the work at their own cost1.
Two details decide whether a cap really protects you.
- The cap must be tied to a defined scope. "Never more than €58,000" means nothing if the supplier can say the remaining work is out of scope. The brief and its acceptance examples set what the cap buys.
- Expect a slightly higher day rate. The supplier now carries the risk above the cap, so they charge for it, usually through the rate rather than a lump sum. That is fair. It is still smaller than a full fixed price margin, because below the cap you carry the risk.
Example: Douglas's cap holds
Douglas charges €620 a day, estimates 80 days, and caps the total at €58,000. In the good case Orla pays 80 days at €620, which is €49,600. In the hard case the 105 days would come to €65,100, but the cap stops the bill at €58,000 and Douglas absorbs the remaining €7,100. Orla's worst case is known before she signs.
What each model is likely to cost: the expected cost
Comparing quotes only on the good case flatters time and materials. Comparing them only on the bad case flatters a fixed price. A fairer comparison weighs each outcome by how likely it is. That weighted average is called the expected cost.
where is the expected cost, the number of possible outcomes, the probability of outcome (all the add up to 1) and what you pay if outcome happens. The idea is explained from scratch in Foundations: expected value.
The expected cost is not what you will pay. You will pay one of the outcomes, never the average. That is why you look at the worst case next to it.
Example: Orla's three quotes, weighed
Orla and her practice manager judge the chance that the insurer link turns out hard at 30%, so for the hard case and for the normal one. (That 30% is their judgement, invented for the example. Why software estimates slip shows how to get a better number than a guess.) For Shandon, she assumes her brief describes the method, so the hard case brings the €18,750 change request.
Shandon, fixed price:
Here is Shandon's expected cost in euro: €60,000 in the normal case, €78,750 with the change request.
Mardyke, time and materials:
Here is Mardyke's expected cost in euro: 80 days or 105 days at €600.
Douglas, capped time and materials:
In each line, and are the probabilities of the normal and the hard case, and the amounts in euro are the costs of each case.
| Supplier | Normal case | Hard case | Expected cost | Worst case | Who carries the overrun |
|---|---|---|---|---|---|
| Shandon, fixed price | €60,000 | €78,750 | €65,625 | €78,750 | Shandon, unless it is a change |
| Mardyke, time and materials | €48,000 | €63,000 | €52,500 | €63,000 | Orla |
| Douglas, capped | €49,600 | €58,000 | €52,120 | €58,000 | Orla up to the cap, then Douglas |
If Orla rewrites the insurer line to describe the result instead of the method, Shandon's hard case stays at €60,000 and its expected cost drops to €60,000. That one sentence is worth €5,625 in expected cost and €18,750 in the worst case.
In this example the capped quote wins on both measures. That is not a law. Change the probability, the cap or the brief, and the order changes. The method is what carries over: list the outcomes, put a cost and a probability on each, and look at the worst case as well as the average.
A paid discovery first, then a fixed price
There is a fourth route, and for a first bespoke project it is often the best one. Split the work into two contracts.
- A short paid discovery. The supplier spends a few weeks understanding the problem, the users and the constraints before anyone commits to the full build. The UK government's service manual describes exactly this phase and says around 4 to 8 weeks is typical for its own services2. A small business project usually needs less. The output is a precise scope, the risky parts tried out for real, and a much better estimate.
- A fixed price (or a capped price) for the build, quoted on that precise scope.
The point of discovery is to turn unknowns into knowns while finding them still costs little. You are not tied to the supplier who did the discovery either: if the contract says the discovery report is yours, any competent supplier can quote on it. (Who owns that report and the code that follows is the subject of who owns the code.)
Example: Orla spends €6,000 to find the problem early
Orla pays Douglas €6,000 for ten days of discovery. On day three they try the insurer link for real, with a test account, and find the daily file upload. Now everyone knows.
Orla has a choice she did not have before. She can include the file upload in the build, now priced on facts, or she can launch without the insurer link, let reception check cover by phone as they do today for the first few months, which is grand for a while, and add the link in a second phase. She chooses the second. The build is quoted at a fixed €50,000 with a much smaller risk margin, because the biggest unknown has been taken out of it.
Total for version one: €6,000 plus €50,000, so €56,000, with almost no hard case left. The insurer link follows later as its own small project, quoted on facts.
Retainers and monthly capacity: for after the launch
A retainer is a monthly fee for an agreed amount of a supplier's time, for example four days a month. You are buying capacity, not a defined result. It suits work that never really ends: fixing small issues, keeping the software and its building blocks up to date, and adding improvements one at a time.
A retainer is a poor way to pay for a first build, because nobody is committed to a result or a date. It is a good way to pay for the years after.
Three things make a retainer fair to you:
- What happens to unused time. Does it roll over to next month, and for how long, or does it lapse?
- How work is agreed. Each piece of work should be described and agreed in writing before it starts, so you both know what the month is buying. I work this way myself for task outsourcing: each task is agreed in writing, and anything not expressly agreed is out of scope.
- Response times. If the booking system stops taking appointments on a Monday morning, how quickly does someone start work on it, and does that come out of the monthly days or on top?
Example: the retainer after launch
After launch, Orla takes a retainer from Douglas of three days a month at €620 a day, so €1,860 a month, with unused days rolling over for one month. In March she uses two days for updates and a fix to the reminder texts. In April she uses four: the one day carried over from March plus three for a new waiting list feature, agreed in writing with a short description and a two day estimate (it took three, and Douglas told her after the second day).
Change requests: how they should be priced
Whatever model you choose, things will change. Your receptionists will try the booking screen and want it different. A new rule from an insurer will arrive. A good contract does not try to prevent change. It makes change predictable.
A change request is a written proposal to change the agreed scope. A fair process has five parts.
- Written, before the work. Never pay for a change you only heard about on the invoice.
- The impact in full. Extra cost, extra days, and the effect on the launch date.
- A rate agreed in advance. The day rate for changes belongs in the original contract, not in the change request.
- A swap option. On a fixed price, you can often swap a feature you no longer need for a new one of the same size at no extra cost, if the contract allows it.
- Your sign off. Nothing changes until you have approved it in writing.
The software world has been arguing about this tension for a long time. The Agile Manifesto of 2001 already put "customer collaboration over contract negotiation" and "responding to change over following a plan" among its four values3. That does not mean contracts do not matter. It means a contract should make change easy to agree, rather than a fight.
Example: the waiting list during the build
Six weeks into Shandon's fixed price build, Orla realises she wants a waiting list: when a patient cancels, the next person on the list gets a text offering the slot. It was not in the brief.
Shandon sends a change request: four days at the contract's change rate of €750, so €3,000, and the launch moves by one week. Orla looks at the scope and finds the printable appointment card, which nobody will use now that reminders are automatic. Shandon agrees it is about the same size. She swaps it out, and the waiting list costs nothing extra. The launch date still moves by three days, which Orla accepts in writing.
Contingency: the money you keep back
Contingency is money you set aside, outside the supplier's quote, for things nobody can foresee. It is not a sign of a bad plan. It is part of a good one.
How much? There is evidence on how badly IT projects overrun. Bent Flyvbjerg and Alexander Budzier analysed 1,471 IT projects and found an average cost overrun of 27%. The average hides the real danger: one project in six overran its cost by 200% on average, and its schedule by almost 70%4. Those were mostly large projects, so read the numbers as a direction, not as a forecast for a clinic's booking system.
Two lessons follow. First, a contingency in the region of 20 to 30% of the estimate is a reasonable starting point for time and materials work. That is my rule of thumb, set against the 27% average, not a figure from the study. Second, no contingency covers a one in six disaster. Only the structure of the deal does that: a cap, a paid discovery that tests the risky part first, and milestones that deliver usable software so you can stop safely.
With a fixed price, you need less contingency for overruns but should still keep some back for changes you will want.
Example: Orla's budget line
For the Mardyke quote, Orla's budget becomes the estimate plus 25%:
where is the budget she sets aside in euro, the supplier's estimate in euro and the contingency as a share of the estimate (here 25%, written as 0.25). The idea of a percentage on top of a base is explained in Foundations: percentages.
Notice where that lands: exactly at Shandon's fixed price. And it still would not cover the hard case of €63,000. That is the real argument for Douglas's cap or for a discovery first. They do not just lower the expected cost, they put a floor under the disaster.
What the law adds when the contract is silent
This is general information, not legal advice. For a contract of this size, a short review by a solicitor is money well spent.
In Ireland, a contract between two businesses for a service is covered by Part IV of the Sale of Goods and Supply of Services Act 1980. Its section 39 implies that a supplier acting in the course of a business "has the necessary skill to render the service" and "will supply the service with due skill, care and diligence"5. Section 40 lets a contract between businesses exclude or vary those terms with an express term, so read any small print that touches them5.
Notice what the Act does not do. Part IV says nothing about the price. Unlike the UK's equivalent, which fills a gap in the contract with "a reasonable charge"6, the Irish Act leaves the price entirely to what you agree. So a vague price is not a low price. It is an argument, settled after the work is done, when you are in the weakest position to argue. Write the price mechanism down: the fixed sum, or the day rate, the cap, the change rate and the payment stages.
The skill and care term is a floor, not a promise of a result. "Due skill, care and diligence" is not the same as "it will work the way I imagined". What counts as done belongs in the contract, which is the subject of acceptance and done.
Example: the clause Orla adds
Orla's contract with Douglas now has a short pricing schedule:
- day rate €620, cap €58,000 for the scope in the brief and its acceptance examples
- changes at €620 a day, agreed in writing before work starts, with the impact on cost and date
- invoices every two weeks with days used and what they were used for
- a written warning within two working days if the forecast to complete passes 80% of the cap
Nothing here is unusual. It simply leaves nothing to an argument after the fact.
Choosing a model, step by step
Put together, the choice follows a few questions about your project, not about the supplier.
Example: Orla walks the questions
- Can the scope be written down precisely? Yes. Her brief has the journeys and an acceptance example for each one.
- Is there a risky unknown? Yes, the insurer link. Nobody has tried it.
- So she takes the recommended path: ten days of paid discovery for €6,000, which finds the daily file upload, then a fixed €50,000 build without the insurer link, then a second small project for the link.
- After launch, a retainer of three days a month.
The questions to ask every supplier about price
Whichever model a supplier offers, these questions show you where the risk really sits. A good supplier answers them without hesitation.
- What exactly does this price cover, and what is excluded?
- If the work takes longer than you think, who pays for the extra time?
- What is your rate for changes, and is it written in the contract?
- How will I see the days used and the forecast to finish, and how often?
- What is the riskiest part of this project, and when will you tackle it?
- Can we stop after a stage and keep what has been built so far?
- When do I pay, and what do I have in my hands at each payment?
- What will running and maintaining this cost each month after launch?
Watch for these warning signs: a fixed price for a vague brief with no questions asked, a day rate with no estimate or reporting, a cap with no defined scope, a change rate that is missing or noticeably higher than the build rate, and payment that runs well ahead of working software. Comparing whole proposals, beyond the price, is the subject of reading a software proposal. The longer view of total cost, including hosting and the risk of depending on one supplier, is in the true cost of outsourcing development.
Prices themselves should never be a mystery. I publish my own package prices and hourly rates, so you can compare before we ever talk.
Example: two answers to question five
Orla asks question five to all three suppliers. Douglas answers: "The insurer link. We would build a test connection in the first week, before the screens." Mardyke answers: "Nothing unusual, it is a standard booking system." The first answer shows the supplier has thought about the risk and plans to meet it early. The second tells Orla that the risk is still there, unexamined, and on her side of the table if she signs a time and materials contract.
Conclusion
No pricing model is safe on its own. A fixed price moves risk to the supplier, but only for what the brief pins down, and you pay a margin for it. Time and materials keeps the price honest and the plan flexible, but the overrun is yours, so you need visibility and contingency. A cap gives you a known worst case. A paid discovery turns the biggest unknown into a fact before you commit the big money. A retainer is for the years after launch, not the first build.
Weigh the outcomes, not just the headline number: list what can go wrong, put a probability and a cost on it, and look at the worst case as well as the average. Then write the answer into the contract, so that nothing about the price is left to an argument after the work is done.